Capacities of Power Plants (MW)

Select Year to

Power Plant (CEB)
   2012 2013 2014 2015 2016
Major Hydro 1,337.00 1,340.50 1,356.50 1,356.50 1,363.40
Small Hydro 20.45 20.45 20.45 20.45 20.45
Sub Total CEB Hydro 1,357.45 1,360.95 1,376.95 1,376.95 1,383.85
Wind 3.00 3.00 3.00 3.00 3.00
Sub Total CEB Non-Conventional 3.00 3.00 3.00 3.00 3.00
Steam, Fuel Oil 0.00 0.00 0.00 0.00 0.00
Steam, Coal 300.00 300.00 900.00 900.00 900.00
Sub Total Steam 300.00 300.00 900.00 900.00 900.00
Diesel Engine, Residual Oil 160.00 160.00 160.00 160.00 160.00
Diesel Engine, Diesel Oil 13.80 0.00 0.00 0.00 0.00
Diesel Engine, Fuel Oil 0.00 24.00 24.00 24.00 0.00
Sub Total Diesel Engines 173.80 184.00 184.00 184.00 160.00
Gas Turbines, Diesel Oil 215.00 215.00 195.00 195.00 195.00
Sub Total Gas Turbines 215.00 215.00 195.00 195.00 195.00
Combined Cycle, Naphtha and Diesel 165.00 165.00 165.00 165.00 165.00
Sub Total Combined Cycle 165.00 165.00 165.00 165.00 165.00
Sub Total CEB Power Plants 2,214.25 2,227.95 2,823.95 2,823.95 2,806.85
Private Power Plant (IPP)
   2012 2013 2014 2015 2016
Diesel Engine, Residual Oil 51.00 51.00 49.00 51.00 51.00
Diesel Engine, Fuel Oil 342.50 280.00 287.00 160.00 160.00
Diesel Engine, Diesel Oil 15.00 0.00 0.00 0.00 0.00
Combined Cycle, Diesel, Fuel Oil 433.00 380.00 433.00 433.00 433.00
Sub Total IPP 841.50 711.00 769.00 644.00 644.00
Private Power Plant (SPP)
   2012 2013 2014 2015 2016
Hydro 227.42 255.78 287.53 306.67 337.92
Combined Heat and Power 0.00 0.00 0.00 0.00 0.00
Solar Power 1.38 1.36 1.36 1.36 21.36
Biomass 10.50 16.00 20.00 20.10 24.10
Wind 73.04 78.45 128.45 123.85 128.45
Sub Total SPP 312.34 351.59 437.34 451.98 511.83
Net-metered Projects (NmP)
   2012 2013 2014 2015 2016
Solar 0.00 3.35 13.27 27.71 50.42
Sub Total NmP 0.00 3.35 13.27 27.71 50.42
Sub Total of Private Power Plants
   2012 2013 2014 2015 2016
Sub Total 1,153.84 1,065.94 1,219.61 1,123.69 1,206.25
Private Power Plants (Hired)
   2012 2013 2014 2015 2016
Diesel Engine, Diesel Oil 0.00 0.00 0.00 0.00 0.00
Total Grid Connected Capacity
   2012 2013 2014 2015 2016
Total 3,368.09 3,293.89 4,043.56 3,947.64 4,013.10
Off-Grid System
   2012 2013 2014 2015 2016
Off-Grid System Industrial 0.00 0.00 0.00 0.00 0.00
Sub Total Off-Grid Conventional 0.00 0.00 0.00 0.00 0.00
Total Generation Capacity
   2012 2013 2014 2015 2016
Total 3,368.09 3,293.89 4,043.56 3,947.64 4,013.10
CEB Grid
   2012 2013 2014 2015 2016
Gross Generation to CEB Grid (GWh) 11,878.85 12,005.55 12,830.11 13,211.07 14,342.56
System Peak Demand (MW) 2,146.00 2,164.20 2,151.70 2,283.40 2,452.90
System Load Factor 63.19 63.33 68.07 66.05 66.75
System Reserve Margin 56.95 52.20 87.92 72.88 63.61
Total Grid Connected Capacity
   2012 2013 2014 2015 2016
CEB Hydro 1,357.45 1,360.95 1,376.95 1,376.95 1,383.85
Thermal 1,695.30 1,575.00 2,213.00 2,088.00 2,064.00
CEB Wind 3.00 3.00 3.00 3.00 3.00
New Renewable Energy 312.34 351.59 437.34 451.98 511.83
Net-metered Projects 0.00 3.35 13.27 27.71 50.42
Share of NRE
   2012 2013 2014 2015 2016
Share of NRE in the Grid % 9.27 10.67 10.82 11.45 12.75